“The APL was designed to support the KCC reform process and therefore phased its activities in a manner that was intended to focus on institutional strengthening in the first phase, to build a solid foundation for expanding the focus on infrastructure investments in later phases,” said Moustapha Ndiaye, country manager for Uganda.
The project had two sub-components, the institutional, and the infrastructure. Progress under the institutional component includes;
- Supported the Organizational Development and Governance at KCCA that led to the development of a comprehensive approach to municipal development
- Reduced overdue liabilities from Ushs 8 billion to Ushs 3 billion
- Increased in the share of KCC own source revenue spent on service delivery from 10% to 30%
- Increase in KCC own source revenue from Ushs 22 billion to Ushs 30 billion
- Increased public satisfaction in service delivery in the following areas: roads from 18% to 50%, drainage from 22% to 31%, and solid waste from 44% to 60%
The focus on institutional outcomes was also supported by the KIIDP APL triggers, such as a new operational organizational system, and the establishment and implementation a formal public consultation process.
Under the infrastructure component, the project supported activities aimed at improving the provision of critical services to the city in the five priority areas which were critical for public confidence and contributed to the economic and commercial development of the city, including drainage system improvement, traffic management, road maintenance and upgrading and solid waste management..
Under the drainage system improvement, the project supported increasing the capacity of the Lubigi primary channel to a total length of 4 km. With the construction of the channel, extreme flooding of the city has been reduced from over 3-4 days to just hours.
“By undertaking remedial measures on four tertiary drainage “black spots” in various parts of the city, there was remarkable reduced flooding with the expansion of the capacities and lining of Lubigi secondary channels from 3.6 km to 4 km,” said Charles Tumwebaze, the project coordinator.
On traffic management, Martin Onyach-Olaa, the WBG project task team leader, noted that traffic congestion in the city has been growing fast due to poor road network, uncontrolled junctions and insufficient road capacity.
“Out of the 1200 km of roads in the city, only about 300 km are paved, and a significant portion of the unpaved network is heavily trafficked with over 300 vehicles per day, Onyach-Olaa said. “In order to address those challenges, KIIDP supported the reconstruction of five major roads in the city.”
The KIIDP also focused on rehabilitating high priority infrastructure, which included the undertaking and maintenance of about 26km of selected tarmac roads and upgrading of about 14.42km of high priority gravel roads to bitumen standard The five roads that were found to be critical to maintaining the productivity and welfare of the city included: Ttula-kawempe road, Kimera – Kasubi road, Kalerwe – Kawempe road, Bukoto – Kisasi road and Soweto – Kasanga road.
“The upgrading of the five major roads led to improved traffic flow through provision of traffic management infrastructure such as guard rails, signs and the improvements in five junctions by providing localized widening and signalizing,” Tumwebaze said.
Under solid waste management, the project supported the extension of Kampala’s biggest landfill – the Kitezi Landfill.
“Kitezi landfill was almost full, but with the support from the World Bank, the landfill was extended by six acres in order to boost its capacity for another three years,” Tumwebaze said.